top of page

Vision 2020:Close the Loop

Whitefish Trail group aims to finish loop by 2020

By MATT BALDWIN Whitefish Pilot | Posted: Tuesday, June 28, 2016 


Whitefish Trail

Hikers head out on the Whitefish Trail June 26 at the Lion Mountain trailhead.

There’s not much vertical relief along the lowlands at the head of Whitefish Lake. Gentle pastures and wetlands stretch from the BNSF Railway tracks to the broad flood plains at Swift Creek. It’s an easy walk or ride along Delray Road to traverse from one side to the other.

From a trail-builder’s perspective, however, this total lack of topography might prove to be the most challenging yet in mapping the future path of the Whitefish Trail as it now progresses to the east side of the lake.


“We’ve got Swift Creek, Lazy Creek, some wetlands and the railroad tracks,” said Greg Gunderson, who is helping design sections of the trail. “You’ve got these four different issues to deal with.”


A pedestrian bridge is needed for the railroad crossing, the wetlands are environmentally sensitive and could require a 1,000-foot boardwalk, while the Swift Creek crossing needs a long span stable enough to support a mountain bike.


Connecting the Beaver Lakes section to the Swift Creek trailhead is just one crux remaining in Whitefish Legacy Partners’ efforts to “close the loop” of the Whitefish Trail. The nonprofit behind the trail-building effort is aiming to complete a 55-mile recreational loop circling Whitefish Lake by 2020.


Gunderson has flagged potential trail routes through the Swift Creek area — nothing has been decided yet — but he’s optimistic it can be done. He describes the landscape as rivaling areas of Glacier National Park.


“In my mind, it’s possible,” he said. “We’ve got this terrain with old growth forest, big trees and beautiful streams, I feel like we have a Glacier Park experience we can provide just minutes from downtown.”


“If we do it right, we can respect the integrity of the environment and the private lands, and do it in a way that will showcase the headwaters of Whitefish Lake.”


The Whitefish Trail effort, decades in the making, began in earnest in 2010 when the first few miles of trail were opened around Lion Mountain. About 36 miles of trail and 10 trailheads have been built since then.


Beyond Swift Creek, preliminary plans show the trail climbing up the lower flanks of Big Mountain into Hellroaring Basin where it then traverses below Elk Highlands to Haskill Basin and eventually into town.


“It’s certainly an exciting time to be thinking about closing the loop,” said Legacy Partners executive director Heidi Van Everen.


“We can see the end. It’s not the final stretch … but we’re on the right track.”


To close the loop means securing between $3 million and $5 million in funding and navigating through a maze of land ownership. The total estimated cost includes planning, design, construction and funding an endowment for ongoing trail upkeep.


Van Everen says they’re eying a Federal Lands Access Grant that could take a significant bite out of the overall price tag.


“We’re hoping to get grants to support 60 percent of the project,” she said. “We need something big.”


The first priority in closing the loop is building the section through Haskill Basin, which received a big boost last week in the form of a $150,000 Land and Water Conservation Fund grant. Along with a required $150,000 match in private donations, the money will fund construction of 5.5 miles of new trail and two new trailheads.


One will be on city-owned property along Reservoir Road and would be similar to a park setting with picnic sites and parking for up to 40 vehicles. The other trailhead on Big Mountain Road just below Whitefish Mountain Resort will also serve as a winter trail groomed for Nordic skiing access. It would be built in partnership with Glacier Nordic Club and the Iron Horse subdivision on an easement provided by Whitefish Mountain Resort.


Van Everen says about $350,000 to $500,000 is needed to complete the Haskill phase, which is anticipated to open next spring.


From there the trail effort will turn to a section from a new trailhead at Holbrook Overlook off Big Mountain Road traveling northwest toward Swift Creek.


Navigating land ownership issues will be a challenge on this stretch, Van Everen said, noting that it’s a mix of Forest Service and private holdings.


“It’s a patchwork of private land owners and we will need their support to complete the vision,” she said.


It’s planned to have the Holbrook to Swift Creek section opened by 2018.


The Swift Creek to Beaver Lake section is tagged to be finished by 2019/2020, representing completion of the project.


Van Everen points out that passing through the wetlands at the lake headwaters and crossing Swift Creek could prove to be cost prohibitive and will likely require some environmental analysis. But it’s worth investigating, she said.


“That section could be the prize of the entire trail system,” Van Everen said. “It’s such a critical area to protect, it will be an important piece to do right.”


Van Everen says momentum from the first 36 miles of trail building will help carry the project into the next and final phases.


“Nobody ever expected we’d have a trail or gotten as far as we have,” she said. “It’s exciting to keep moving and prove we can create this amenity for the community.”


Gunderson agrees, saying that completing the loop would be of national significance.


“The Whitefish Trail would qualify as a national recreation trail. It will be that level of experience,” he said. “What started as a dream is nearing reality.”

Comments


bottom of page